Image of picture line

CR3.0 Assessment and Certification of Feed Responsibility Assurance scopes

icon

This document is available in 3 different languages

Version: 2 March 2026

Download PDF

1. Scope of this document

This document contains assessment and certification/inspection criteria for:

  • Feed Responsability Assurance Module (FRA).

2. Normative references

The following documents, in whole or in part, are normatively referenced in this document and are mandatory to comply with. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.

3. Terms and Definitions

For GMP+ definitions see F0.2 Definition list. Throughout this document the terminology “through the Certification Body” is used indicating that all activities performed by critical-, non-critical locations are conducted under the responsibility/liability of the GMP+ accepted Certification Body.

4. Process requirements

4.1. Pre-certification activities

4.1.1. Application

The Certification Body must require an authorized representative of the applicant organization to provide the necessary information to enable it to establish the following:

  1. the desired scope of the certification;
  2. relevant details of the applicant organization as required by the specific certification scheme, including its name and the address(es) of its site(s), its processes and operations, human and technical resources, functions, relationships and any relevant legal obligations;
  3. identification of outsourced processes used by the organization that will affect conformity to requirements;
  4. the standards or other requirements for which the applicant organization is seeking certification;

Relevant details of the applicant organization including its name and addresses as specified in the official legal business registration by the competent authority and information as mentioned in Appendix 2 of this document. In addition the 5th bullet of article 5.1.1. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes, applies.

4.1.2. Application review

Before proceeding with the audit, the Certification Body will carry out a review of the application and additional information for certification to ensure that:

  1. the information about the applicant organization and its management system is sufficient for the conduct of the audit;
  2. any known difference in understanding between the Certification Body and the applicant organization is resolved;
  3. the Certification Body has the competence and ability to perform the certification activity;
  4. the scope of certification sought, the location(s) of the applicant organization's operations, time required to complete audits and any other points influencing the certification activity are taken into account (language, safety conditions, threats to impartiality, etc.);
  5. records of the justification for the decision to undertake the audit are maintained.

The certification body, following the review of the application, must either accept or decline an application for certification (the reasons for declining an application, the review of the application, must be documented and made clear to the client).

Based on the review, the Certification Body must determine the competences it needs to include in its audit team and for the certification decision.

The Certification Body must not exclude activities, processes, products and services from the scope of certification when these can have an influence on the feed responsibility. The application review is mandatory.

4.1.3. Certification agreement

Article 5.1.3 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable. In deviation on requirement 5.1.3.b, the minimum obliged audit/inspection time per scope(s)/standard(s) as stated in Appendix 1 of this document per audit type is applicable, referring to Appendix 1 is insufficient.

4.1.4. Audit team assignment

Persons who are performing the audit must comply with the applicable requirement of Appendix 2 of the CR1.0 Acceptation requirements.

4.1.5. Rotation of auditors

Rotation of FRA auditors :

4.1.6. Audit plan

An audit plan for each type of audit must be send to the GMP+ Certified Company prior to the audit.

4.2. Certification process

4.2.1. Audit

4.2.1.1. General

Article 5.2.1.1. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable. The minimum obliged audit frequency and audit times are determined in Appendix 2 of this document (CR3.0).

4.2.1.2. Initial certification Audit and inspection

An initial certification audit will be performed through the Certification Body in order to assess whether the company meets the criteria set out in Appendix 1 of this document. The initial certification audit must be conducted within 3 months after concluding a certification agreement with the applicant organization.

When the specific conditions as described in Appendix 4 “Not at the GMP+ Certified Company location” and/or Appendix 5 “Remote Audits” of this document are met, the Initial certification audit can be performed accordingly.

4.2.1.3. Temporary acceptance

The text of article 5.2.1.3.1 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.2.1.4. Surveillance audits

The first surveillance audit must be executed each 12 months, plus and minus 2 months, after the certification decision date.

The second surveillance audit must be executed each 24 months, plus and minus 2 months, after the certification decision date.

When the specific conditions as described in Appendix 4 “Not at the GMP+ Certified Company location” and/or Appendix 5 “Remote Audits” are met, the surveillance audit can be performed accordingly.

4.2.1.5. Announced surveillance audits

An announced surveillance certification audit will be performed during the period of validity of the GMP+ certificate through the Certification Body in order to assess whether the company meets the criteria set out in Appendix 1 of this document. The frequency and the audit times of the announced surveillance audit are determined in Appendix 2 of this document.

4.2.1.6. Unannounced surveillance audits

See article 4.2.1.5 above. In addition if the FRA module is audited together with the FSA module the audit will be performed unannounced for all scopes.

4.2.1.7. Recertification audit

Prior to the extension of validity of a certificate a re-certification audit/inspection must be carried out through the Certification Body.

A GMP+ certificate may or may not be extended by the Certification Body based on the assessment criteria as specified in Appendix 1 this document.

Before the period of validity of the certificate expires, the total certification process must be finished including updating of the GMP+ company database (status and data of certificate) through the Certification Body. If a recertification audit is not carried out before the expiration date of the validity of the certificate, then an initial certification audit must be carried out. The company is in the intervening period not GMP+ certified.

When the specific conditions as described in Appendix 4 “Not at the GMP+ Certified Company location” and/or Appendix 5 “Remote Audits” are met, the recertification audit can be performed accordingly

4.2.1.8. Expansion audit

Article 5.2.1.7. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.2.2. Special audits

The following audits can be applicable, assessment must be done in accordance with Appendix 1 of this document.

4.2.2.1. Stricter supervision Audit (SSA)

Article 5.2.2.1. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.2.2.2. Repeat audit (RPA)

Article 5.2.2.2. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.2.3. Extraordinary events

Article 5.2.3. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.2.4. Identifying and Recording Audit findings

If the applicant organization/GMP+ Certified Company does not comply with the applicable requirements of the GMP+ Feed Certification scheme, the sanctions as specified in Appendix 1 of this document apply.

If nonconformity identified in one of the MI5.4 GMO controlled scopes this applies for both the FRA and FSA scopes.

4.2.5. Audit report

The text of article 5.2.6. and Appendix 3 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.2.6. Review

Article 5.2.7. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.2.7. Certification decision

The certification decision must be based on:

  1. For any type of nonconformities, the Certification Body has reviewed, accepted and verified the correction and corrective actions;
  2. Assessment of the applicant organization/GMP+ Certified Company took place in accordance with Appendix 1 of this document.
  3. The assessment and decision of a Certification Body must be demonstrably based on objective evidence of conformity and non-conformity obtained.

4.2.8. Certificate and Temporary acceptance

4.2.8.1. Certificates/ Statement

A certificate has the following maximum validity:

  • FRA certificates (all MI 5.1, MI 5.2, MI 5.3, MI 5.4, MI 5.6 and MI5.7): 3 years,
  • FRA statement (MI 5.5): 14 months

calculated from the date of a positive certification decision. Within 8 weeks following the execution of the audit on site, the Certification Body will send the certificate/ statement to the applicant organization/GMP+ Certified Company. The duration of the GMP+ certificate/ statement must not exceed the validity of the certification agreement.

4.2.8.2. Temporary acceptance

For FRA temporary acceptance see article 5.2.9.2 of CR2.0 Assessment and Certification of Feed Safety Assurance scopes. However, if during the initial certification audit on site (if applicable), the applicant organization does not appear to comply the GMP+ requirements conform Appendix 1 of this document (CR3.0) then the temporary acceptance must be withdrawn.

4.2.8.3. Certificate and Temporary acceptance templates:

The Certification Body must put the following text on the certificate or temporary acceptance:

  1. Text for a certificate

Name of the Certification Body:

GMP+ International registration number of the Certification Body:


Certificate

GMP+ FRA logo

Name, address, location of the GMP+ Certified Company

(Address where GMP+ activities take place)

GMP+ International registration number of the GMP+ Certified Company


FIXED SECTION

=name CB= declares that there is justifiable confidence that the GMP+ scope(s) =as mentioned in F0.3 Scopes for certification= at the GMP+ Certified Company =name of GMP+ Certified Company= comply with the applicable requirements and conditions of the GMP+ Feed Responsibility Assurance Module 2020.


The Feed Management system of the whole multi-site construction is certified and the validity of this certificate depends on the validity of the certificate of the main office1


FREE SECTION

See F0.3 Scopes for certification - Optional Specification


Registered office of the Certification Body


Certificate number


Start date and end date of certificate

1 Only in case of an individual multi-site certificate, these sentences must be included in the certificate

  1. Text for temporary acceptance

Name of the Certification Body:

GMP+ International registration number of the Certification Body:

Temporary Acceptance


Name, address, location of the temporary accepted company

(Address where GMP+ activities take place)

GMP+ International registration number of the temporary accepted company


FIXED SECTION

=name CB= declares that there is justifiable confidence that the GMP+ scope(s) =as mentioned in F0.3 Scopes for certification= at the GMP+ temporary accepted company =name of GMP+ temporary accepted company= comply with the criteria of a stage 1 assessment of the applicable requirements and conditions of the GMP+ Feed Responsibility Assurance Module 2020.

“ The Feed Management system of the whole multi-site construction is temporary accepted and the validity of this temporary acceptance depends on the validity of the temporary acceptance of the main office”1


FREE SECTION

See F0.3 Scope for certification - Optional Specification


Registered office of the Certification Body

Temporary acceptance number

Start date and end date of temporary acceptance

1 Only in case of an individual multi-site certificate, these sentences must be included in the certificate

  1. Text for statement

Name of the Certification Body

GMP+ International registration number of the Certification Body


STATEMENT


GMP+ FRA logo


The Certification Body [Name CB] states that company Y

Name, location of company Y

Visiting address and location of company Y

GMP+ International registration number of the company location visited


was inspected in accordance with the applicable requirements of MI5.5 Carbon footprint of feed - Nevedi Protocol and CR3.0 Assessment and Certification of Feed Responsibility Assurance scopes of GMP+ International B.V. in Rijswijk, The Netherlands.


The Certification Body [name CB] states, based on this inspection, that the company [name Company Y] complies with the requirements of MI5.5 Carbon footprint of feed - Nevedi Protocol. This statement applies to:


  • All feed produced by [name Company]

or

  • Feed produced by [name Company] for [animal species 1]
  • Feed produced by [name Company] for [animal species 2]
  • Feed produced by [name Company] for [animal species 3]


Date of inspection:



Registered office of the Certification Body:

Statement number:

Statement start date:

Statement end date:

Next inspection to be conducted prior to date:

In addition the following applies for the above certificate, temporary acceptance and statement:

  1. The data of the GMP+ Certified Company/temporary accepted company must exactly be the same as registered in the legal business registration. (for example Chamber of Commerce/registration at competent authority, tax/vat number)
  2. It is mandatory to show the GMP+ FRA logo on the certificate.
  3. It is not permitted to use the GMP+ FRA logo on a temporary acceptance. In addition, the document may not be called a “certificate” but must be designated as a “temporary acceptance”.
  4. It is not permitted to use the logos of Critical Location and non-Critical Location on the GMP+ certificate and temporary acceptance other than the GMP+ accepted Certification Body.
  5. The start date of the certificate/temporary acceptance is a date which is in any event equal or after the date of the positive certification/temporary acceptance decision.
  6. In case of expansion of scopes the end date of the valid GMP+ certificate may not be extended. The Certification Body can also grant the GMP+ Certified Company a new GMP+ certificate for the additional scope.
  7. It is not permitted to specify brand names in any way whatsoever on the certificate or temporary acceptance.
  8. (Contractual) conditions/ requirements are not allowed on the GMP+ certificate/temporary acceptance/statement.

4.3. Suspension or Withdrawal of a Certificate Temporary acceptance

The text of article 5.3 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.4. Transfer to another Certification Body

Article 5.4. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.4.1. Pre-transfer review

Article 5.4.1. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.4.2. Certification process during transfer

Article 5.4.2. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

4.4.3. Cooperation between the departing and accepting Certification Bodies

Article 5.4.3. of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable

5. Exclusion of GMP+ International Liability

Chapter 6 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable.

6. Tariffs

The Certification Body will use its own tariff. On behalf of GMP+ International, through the Certification Body, relevant tariff as listed in GMP+ CR4.0 Tariffs are charged.

7. Disputes between Certification Bodies and GMP+ certified companies

Disputes between Certification Bodies and applicant organization/GMP+ Certified Companies with respect to the assessment will initially be handled in accordance with the dispute regulation of the Certification Body. If this does not lead to a solution, then the dispute can be handled in accordance with the F0.5 Disputes procedure.

Appendix 1: Assessment criteria and sanctions for audits GMP+ FRA

Non-conformities are to be classified based on:

  • The general assessment criteria as mentioned in this Appendix
  • The specific assessment criteria as shown in the checklists.

The sanctions specified must be imposed as a minimum. Through the Certification Body it is allowed to impose stricter sanctions.

If in this table is mentioned certificate it also applies for the temporary acceptance.

Classification: Minor non-conformity

Description

Consequences

Period to close

ICA/RCA

SA

GMP+ Certified Companies:

  • do not comply with GMP+ requirements, incidental nature and feed responsibility is not adversely affected.

< 10 non-conformities

Certificate can be issued

Certification can be continued

during next on-site audit

≥ 10 non-conformities

Certificate cannot be issued

Certification can be continued

within 6 weeks

Classification: Major non-conformity

Description

Consequences

Period to close

ICA/RCA

SA

GMP+ Certified Companies:

  • cannot close previous minor nonconformity within the deadline as agreed with
    Certification Body;
  • structural non-conformity and feed responsibility is not adversely affected;
  • do not comply with legislation;
  • do not comply with GMP+ requirements and feed responsibility may be adversely affected.

Certificate cannot be issued

Certification can be continued but a stricter supervision audit may be performed (see Art. 5.2.2.1 of CR2.0)

within 6 weeks

Classification: Critical nonconformity

Description

Consequences

Period to close

ICA/RCA

SA

GMP+ Certified Companies:

  • cannot close previous major nonconformity within the deadline as agreed with Certification Body;
  • structural non-conformity and feed responsibility may be adversely affected;
  • do not comply with GMP+ requirements incidental nature and feed responsibility is adversely affected;
  • under impending prosecution resulting in direct/possible feed responsibility hazard.
  • reasonably assumed to commit gross negligence, fraudulent actions or economic malpractice and feed responsibility is/can be adversely affected.

Certificate cannot be issued

*Level 1. Certification can be continued but stricter supervision audits must be performed (see Art. 5.2.2.1 of CR2.0)

Within 2 weeks

*Level 2. Certificate must be suspended: maximum 3 months

Lifting of *level 2: Certificate can be continued only possible if the Certification Body can close the critical non-conformity during stricter supervision audit (see Art. 5.2.2.1 of CR2.0)

*Level 3. Certificate must be withdrawn at least 1 year excluded from participation in the GMP+ Feed Certification scheme, as well as all Gatekeeper Options

GMP+ Certified Companies:

  • do not cooperate in (planning/conducting) audits by Certification Bodies and/or GMP+ International (not applicable for ICA)
  • do not comply with GMP+ requirements structural nature and feed responsibility is adversely affected

Certificate cannot be issued

*Level 1. Certificate must be suspended: maximum 3 months

Lifting of *level 1: Certificate can be continued only possible if the Certification Body can close the critical non-conformity during stricter supervision audit (see Art. 5.2.2.1 of CR2.0)

*Level 2. Certificate must be withdrawn at least 1 year excluded from participation in the GMP+ Feed Certification scheme, as well as all Gatekeeper Options

* Sanctions can be applied starting at any level.

Appendix 2: Frequency and Audits times

See Appendix 2 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes. The audit times in Table 1 below are in addition to a GMP+ FSA scope (or equivalent as mentioned in chapter 3 of TS1.2 Purchase). Reduction of audit times for the applicable FRA scopes in Table 2 only applies when the audit is simultaneously performed with the FSA scopes (or equivalent as mentioned in chapter 3 of TS1.2 Purchase) by the same audit team. The audit team assessing the FRA scopes must have a valid GMP+ acceptation covering the relevant FRA scopes. These audit times include preparation, reporting and audit time reduction is not allowed.

Ranking of scope groups

For calculating the minimum audit time, the group of FRA scopes must be ranked as follows:

  • scope group A: GMO – Controlled
  • scope group B: RTRS, Responsible pig & poultry feed, Responsible dairy feed, Responsible feed
  • scope group C: Feed environmental footprint
Ranking of Supply chain models

For calculating the minimum audit time, the audit time for each supply chain model shall be ranked as follows:

  • Segregation
  • Mass Balance, Area Mass Balance, Book & Claim.
Formula for calculation

For calculating the minimum obliged (Initial Certification audit (ICA); (Un)Announced Surveillance audit (USA/ASA) and Recertification audit (RCA)) audit time for a single site the following formula will be used:

Ts= TD + TH1 + TH2 (if applicable)+ TFTE

Where:

Ts: minimum obliged audit time, in days

TD: the sum of the basic audit time of the first scope per scope group (A, B, C), in days;

TH1: the sum of the audit time for each additional GMP+ FRA scope for scope group A, in days;

TH2: the sum of the audit time for each additional supply chain model per individual scope in scope group B, in days;

TFTE: : Is the number of audit days per number of employees.


Table 1

Stand alone for each additional location

Scope group

Scope of certification

Supply chain model

Minimum audit times in days (all types of audits)

Basic audit times (TD)

Each additional GMP+ FRA scope (TH1)

Each additional supply chain model (TH2)

Total no. of employees (FTE3 relevant for personnel related to all GMP+ activities, expressed in audit days ) (TFTE)

B.

RTRS1+2

Segregation

0,5

N.A. all scopes within group B are considered as one scope when calculating audit times.

+ 0,125

1 to 19 = 0


20 to 49 = 0,125


50 to 79 = 0,25


80 to 200 = 0,375


>200 = 0,5

Mass Balance4

0,375

Responsible pig & poultry1+2

Segregation

0,5

Mass Balance4

0,375

Area Mass Balance4

0,375

Book & Claim4

0,375

Responsible dairy1+2

Segregation

0,5

Mass Balance4

0,375

Book & Claim4

0,375

Responsible feed1+2

Segregation

0,5

Mass Balance4

0,375

Area Mass Balance4

0,375

Book & Claim4

0,375

Each additional production location audited

0,375

N.A.

+ 0,125

  1. If an invoicing address is applicable the minimum obliged audit time is 0,125 days.
  2. If a PO-box is applicable the minimum obliged audit time is 0,125 days.
  3. Number of employees is including part-time workers calculated as percentage of FTE.
  4. For each additional production location audited see also Table 3 if applicable.
Table 2
In combination with a GMP+ FSA scope (or equivalent as mentioned in chapter 3 of TS1.2 Purchase) at the same location



Minimum audit times in days (all types of audits)
Scope group Scope of certification Supply chain model Basic audit times (TD) Each additional GMP+ FRA scope (TH1) Each additional supply chain (TH2) TFTE

A.

Production of compound feed - GMO Controlled

N.A.

0,125

+ 0,125

N.A.

See CR 2.0

Production of premixtures - GMO Controlled

0,125

Production of feed additives - GMO Controlled

0,125

Production of feed materials - GMO Controlled

0,125

Trade in feed - GMO Controlled

0,125

Storage and Transshipment of feed - GMO Controlled

0,125

Road transport of feed - GMO Controlled

0,125

Each additional production location audited

0,125

+ 0,0632

B.

RTRS

Segregation

0,125

N.A. all scopes within group B are considered as one scope when calculating audit times.

+ 0,063

Mass Balance1

0,125

Responsible pig & poultry feed

Segregation

0,125

Mass Balance1

0,125

Area Mass Balance1

0,125

Book & Claim1

0,125

Responsible dairy

Segregation

0,125

Mass Balance1

0,125

Book & Claim1

0,125

Responsible feed

Segregation

0,125

Mass Balance1

0,125

Area Mass Balance1

0,125

Book & Claim1

0,125

Each additional production location audited

0,125

N.A.

+ 0,0632

C

Feed environmental footprint

N.A.

0,375

N.A.

N.A.


Each additional production location audited

0,125

N.A.

  1. For each additional production location audited see also Table 3 if applicable.
  2. For more than 5 additional production locations, TH1 and TH2 must be 0,125 days.

When a main office has additional production location(s) and the following conditions are met, Certification Bodies can decide to audit the additional production location(s) from the main office, and the minimum obliged audit times in Table 3 are applicable for the main office.

  • All FRA scopes certified at each additional production location, as specified in Table 3, must be secured in the feed responsibility management system (FRMS) of the main office.
  • The main office is fully responsible for managing a common material accounting system that secures all scopes and supply chain models, and the same calculation tool(s) used at all additional production locations.
  • The main office holds full responsibility and performs the following activities for all additional production locations:
    • purchase of ingredients/raw materials of final feed products produced by the additional production location(s),
    • formulation of product recipes of final feed products produced by the additional production location(s),
    • sales of final feed products produced by the additional production location(s),
    • production planning and/or transport planning of final feed products produced by the additional production location(s),
    • collection and calculation of relevant data for feed environmental footprint of all additional production location(s),
    • all relevant documentation is (digitally) available at the main office.

For calculating the minimum obliged (Initial Certification audit (ICA); (Un)Announced Surveillance audit (USA/ASA) and Recertification audit (RCA)) audit time for each additional production location(s). The following formula must be used:

Ts= TD + TH1

Where:

Ts: minimum obliged audit time for additional production location(s) that can be audited from the main office, in days.

TD: the sum of the audit times per scope to be added to the main office, in days.

TH1: the sum of the audit time for each additional supply chain model for per individual scope in scope group B, in days.

Table 3. Audit times for max. 5 additional production location(s)

Scope group

Applicable scope

Supply chain model

Basic audit times (TD)

Each additional supply chain model (TH1)1+

B.

RTRS

Mass Balance

0,125

+ 0,063

Responsible pig & poultry feed

Mass Balance

0,125

Area Mass Balance

Book & Claim

Responsible dairy

Mass Balance

0,125

Book & Claim

Responsible feed

Mass balance

0,125

Area Mass Balance

Book & Claim

C.

Feed environmental footprint

N.A.

0,125

N.A.

  1. For more than 5 additional production locations, TH1 must be 0,125 days.

Appendix 3: Multi-site certification

Appendix 4 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes is applicable. In addition:

Multi-site certification is not permitted for the FRA scopes:

  • Production of compound feed - GMO controlled,
  • Production of premixtures - GMO controlled,
  • Production of feed materials - GMO controlled,
  • Production of feed additives - GMO controlled.

Multi-site certification is permitted for the FRA scopes:

  • Trade in feed - GMO controlled,
  • Storage and Transshipment of feed - GMO controlled,
  • Road transport of feed - GMO controlled,
  • RTRS*
  • Responsible pig & poultry feed*
  • Responsible dairy feed*
  • Feed environmental footprint*
  • Responsible feed*

* With the exception of:

  • any location which is certified for the aforementioned scopes that produces feed products;
  • when these scopes are audited in combination with a scope for which multi-site certification is not allowed (both FRA and FSA scopes).

Helpful tip

If, for example, a group of companies consist of multiple production locations and trade locations, the production locations in this group cannot be certified under multi-site but for the trade locations this is possible.

Audit frequency for a multi-site organization:

  • With a main office and equal or less than 20 multi-site locations, all multi-site locations must be audited at least once during one certification cycle.

With a main office and more than 20 multi-site locations, all multi-site locations must be audited at least once during two consecutive certification cycles.

Minimum obliged audit time in day’s per multi-site location

Scope group Location
Minimum audit times
Main office


Audit time mentioned in Appendix 2 increase with extra audit time per multi-site location of 0,253¹ day up to a maximum of 1,25 day.

Multi-site location First supply chain model/ calculation tool Minimum audit times Each additional supply chain model/calculation tool
A.

Trade in feed - GMO Controlled

N.A.

0,125

N.A.

Storage and Transshipment of feed – GMO Controlled

0,125

Road transport of feed – GMO Controlled

0,125

Both Storage and Transshipment of feed and Road transport of feed – GMO Controlled

0,125

Storage and Transshipment of feed and/or Road transport of feed and/or limited Trade in feed – GMO Controlled

0,25

B. RTRS3+4 Segregation 0,125 +0,063
Mass Balance 0,125
Responsible pig & poultry feed3+4 Segregation 0,125
Mass Balance 0,125
Area Mass Balance 0,125
Book & Claim 0,125
Responsible dairy feed3+4 Segregation 0,125
Mass Balance 0,125
Book & Claim 0,125
Responsible feed3+4 Segregation 0,125
Mass Balance 0,125
Area Mass Balance 0,125
Book & Claim 0,125
Feed environmental footprint3 N.A. 0,125 +0,063
Multi-site location PO-Box2 N.A. 0,125 N.A.
Multi-site location invoicing address2 N.A. 0,125 N.A.

1 If the multi-site is a PO-Box and/or an invoicing address, no additional audit time at the main office is applicable.

2 Audit times are not applicable in combination with an FSA invoicing address/ PO box.

3 Certification Bodies can decide to audit the multi-site location(s) from the main office. This is only applicable for scope group B (excluding supply chain model Segregation) and C when the following conditions are met.

  • All FRA scopes certified at each multi-site location(s), as specified in the table, must be secured in the feed responsibility management system (FRMS) of the main office.
  • The main office is fully responsible for managing a common material accounting system that secures all scopes and supply chain models and the same calculation tool(s) used at all multi-site locations.
  • The main office holds full responsibility and performs the following activities for all multi-site locations:
    • purchase and/or sales of feed products covered by the applicable scopes(s) from multi-site locations,
    • planning transport, storage and transshipment activities,
    • collection and calculation of relevant data for feed environmental footprint of all multi-site location(s),
    • all relevant documentation is (digitally) available at the main office.
4 all scopes within group B are considered as one scope when calculating audit times.

Appendix 4: Auditing not at the GMP+ certified company location

The requirements as stated in Appendix 5 of CR2.0 Assessment and Certification of Feed Safety Assurance scopes are applicable for the following scopes:

  • Trade in feed – GMO Controlled;
  • Road transport of feed – GMO Controlled;
  • Road transport of feed – GMO Controlled mandatory sub-scope Tractionair;
  • “Invoicing Address”;
  • “PO-Box”.

Appendix 5: Remote audits

If an audit is performed in combination with a FSA scope then the requirements as stated in Appendix 6 of the CR2.0 Assessment and Certification of Feed Safety Assurance scopes prevail.

Full Remote Audit

Guided Remote Audit

Applicability

During the regular certification cycle

During extraordinary events

During extraordinary events

FRA Scopes

  • RTRS1
  • Responsible pig & poultry feed1
  • Responsible dairy feed1
  • Trade in feed -GMO controlled
  • Road transport of feed – GMO controlled (only for multisite mandatory sub-scope tractionair)
  • Feed environmental footprint1
  • Responsible feed1

  • RTRS
  • Responsible pig & poultry feed
  • Responsible dairy feed
  • Trade in feed -GMO controlled
  • Road transport of feed – GMO controlled (only for multisite mandatory sub-scope tractionair)
  • Feed environmental footprint
  • Responsible feed

  • RTRS
  • Responsible pig & poultry feed
  • Responsible dairy feed
  • Trade in feed -GMO controlled
  • Road transport of feed – GMO controlled (only for multisite mandatory sub-scope tractionair)
  • Feed environmental footprint
  • Responsible feed
  • Production - GMO controlled (all scopes)
  • Storage and transshipment of feed – GMO controlled

Type of audit

  • Surveillance audit2 (Announced and Unannounced)
  • Expansion audit2
  • Adding a multi-site location3

  • Initial Certification audit3
  • Surveillance audit (Announced and Unannounced)
  • Recertification audit
  • Expansion audit3
  • Adding a multi-site location3

  • Initial Certification audit3
  • Surveillance audit (Announced and Unannounced)
  • Recertification audit,
  • Expansion audit3
  • Adding a multi-site location3.

Specific Requirements

Prior to the audit, the Certification Body must perform and document a risk assessment with at least the following risks that have a significant impact on the audit:

  • Use of the ICT tools: familiarity of the auditor, guide and the auditee with the communication application (Skype, Microsoft Teams, Zoom, etc.);
  • Possibility of using cameras during the whole audit (incl. plant tour) – live connection;
  • Availability of a secure ICT tool for transferring documents and screensharing;
  • Availability of FRMS documents/ records in electronic format;
  • Forgery of the digital evidences;
  • Quality of the Internet connection between auditor, guide and auditee;
  • Impact on the audit planning;
  • Impact on the audit duration;
  • Impact on audit agenda;
  • Impact on audit preparation;
  • The way of performing a remote audit;
  • Auditor and auditee capability of communicating (incl. reading and understanding the FRMS documents);
  • Maturity of the certified organization’s FRMS and nonconformity history;
  • Time zone difference between auditor and auditee (when applicable);
  • The site’s operability of the process for which the company is certified;
  • Auditor has sufficient knowledge of the company (size, complexity, processes, interactions, etc.);
  • When applicable, Assessment of previous report.
  • When applicable, the experience of the last remote audit.

Same requirements for the risk assessment prior to the audit, as for Full remote audit during regular certification cycle.

Same requirements for the risk assessment prior to the audit, as for Full remote audit during regular certification cycle.

The Certification Body must secure the Guide’s impartiality and keep it as documented information.

Audit Time

Appendix 2 of the GMP+ CR3.0.

70% of the audit time must be spent connected with the auditee using ICT tools.

Appendix 2 of the GMP+ CR3.0.

70% of the audit time must be spent connected with the auditee using ICT tools.

Appendix 2 of the GMP+ CR3.0

70% of the audit time must be spent connected with the auditee and Guide using ICT tools.

Audit team competences

Auditor competencies as per GMP+ CR1.0

Auditor competencies as per GMP+ CR1.0


Auditor competencies as per GMP+ CR1.0

It is the responsibility of the Certification Body to determine if the Guide is competent.

During the audit, the Guide is under the responsibility of the GMP+ accepted auditor of the Certification Body and must not draw conclusions during the audit

General Requirements

Follows the remaining requirements for the certification process as for a regular on-site audit

Follows the remaining requirements for the certification process as for a regular on-site audit

Follows the remaining requirements for the certification process as for a regular on-site audit

1If a company is acting as a main office for a production location(s), the full remote audit is not allowed.

2 If a company is acting as a main office of a multi-site construction, the full remote audit is not allowed.

3 Excluding the scopes which physically handle feed: Production – GMO controlled (all scopes), Storage and transshipment of feed – GMO controlled, Road Transport of feed – GMO controlled. (also not in combination with one of the other service scopes).